Nasir Khan
Construction Update as on 27-February-2019

Construction Update as on 27-February-2019

Tower-A-Pop 9th-floor slab casting completed. 5th-floor brickwork in progress. 10th-floor column Shuttering and casting in progress. Tower-B-Jazz Internal plaster completed. Paint 1st coat up to 18th floor completed. Wall tiles up to 13th floor completed. Floor tiles up to 8th floor in progress. POP work up to 19th floor completed. External plaster non-tower area unit […]

Read More
Nasir Khan

Construction Update as on 24-November-2018

Tower- Trance 22nd-floor brickwork complete. 17th-floor plasterwork in progress. 11th-floor toilet plumbing fitting progress. 19th-floor railing in progress. 12th-floor kitchen counter in progress. Tower- Jazz Plaster internal total complete. Paint 1 coat 18th floor. Wall tiles 13 floors in progress. POP work 19th floors complete. Water Tank ready for casting both. External plaster non-tower area […]

Read More
Nasir Khan
Construction update as on-24-Oct-2018

Construction Update as on 24-October-2018

Read More
Nasir Khan
Rhythm-CCounty-Construction-update-as-on-11-September-2018

Construction Update as on 11-September-2018

 

Read More
Nasir Khan
Rhythm CCounty Construction Update

Construction Update as on 24-April-2018

“TOWER JAZZ” ✔ 12th floor wall tiles in progress ✔ 18th floor main staircase side ✔ 22nd floor plastered work in progress ✔ External plaster in progress “TOWER TRANCE” ✔ 21st floor brick work in progress ✔ 16th floor plaster work in progress “TOWER POP” ✔ 8th floor roof shuttering complete ✔ 4th floor work […]

Read More
Nasir Khan
Construction update as on-09-Feb-18

Construction Update as on 09-February-2018

  ✔ Tower “JAZZ” 19th floor plaster work in progress. ✔ Tower “JAZZ” Toilet wall tiles 9th floor in progress. ✔ Tower “JAZZ” External plaster in progress. ✔ Tower ” JAZZ” 17th floor paint work in progress. ✔ Tower “JAZZ” water tank wall shuttering in progress. ✔ Tower “TRANCE” 22nd floor roof slab steel banding […]

Read More
Nasir Khan
Rhythm CCoutny Construction update 22 December

Construction Update as on 22-December-2017

✔ “Tower B-JAZZ” Finishing work going on. ✔ “Tower A-POP” 7th floor casting & brick work started. ✔ “Tower C-TRANCE: 22nd floor running and 18th floor brick work started. ✔ Club- Finishing work and interior work going on. ✔ Swimming Pool- finishing work going on.

Read More
Nasir Khan
Rhythm CCounty construction update as on-26-Oct-2017

Construction Update as on 26-October-2017

✔ Tower “JAZZ” 22nd floor structure completed – brick work completed till 20th. ✔ Tower “TRANCE” 20th floor structure completed – brick work completed till 16th. ✔ Tower “POP” 6th floor structure completed. ✔ Swimming Pool interior work in progress.

Read More
Nasir Khan
Construction update as on 7-Oct-17

Construction Update as on 07-October-2017

Read More
Nasir Khan

Construction Update as on 11-September-2017

 

Read More

Contact US

Toll Free : 1800 10 222 82
SMS   RC   to 56677
Logo

Site Address

Plot No GH-16-E, Sec-1, Greater Noida (West)

Corporate Office

Rhythm CCounty, Sec-1, Greater Noida (West) - 201306

Life at Rhythm Ccounty

Musical Theme Project Features / Amenities Life @ Rhythm CCounty Take a Virtual Tour

About the Project

Floor Plans Site Layout Pricing List & Payment Plan Download Brochure

Resources

EMI Calculator Steps To Buy 50 Ways to Live Vaastu Shastra