Category: Development News

Rhythm CCounty Construction

Construction update as on 4-July-2019

By ClientClient/ no comments
Tower: A (POP) 9th Floor Slab Casting in progress. 5th-floor brickwork in progress. Tower: (B)-JAZZ Plaster internal total complete. Paint 1 coat 18th floor. Wall tiles 13 floors in progress.
Client
Rhythm CCounty Construction

Construction Update as on 27-February-2019

By ClientClient/ no comments
Tower-A-Pop 9th-floor slab casting completed. 5th-floor brickwork in progress. 10th-floor column Shuttering and casting in progress. Tower-B-Jazz Internal plaster completed. Paint 1st coat up to 18th floor completed. Wall tiles
Client
Rhythm CCounty Construction images

Construction Update as on 24-November-2018

By ClientClient/ no comments
Tower- Trance 22nd-floor brickwork complete. 17th-floor plasterwork in progress. 11th-floor toilet plumbing fitting progress. 19th-floor railing in progress. 12th-floor kitchen counter in progress. Tower- Jazz Plaster internal total complete. Paint
Client
Rhythm CCounty Construction images

Construction Update as on 24-October-2018

By ClientClient/ no comments
Client

Construction Update as on 11-September-2018

By ClientClient/ no comments
 
Client

Construction Update as on 24-April-2018

By ClientClient/ no comments
“TOWER JAZZ” ✔ 12th floor wall tiles in progress ✔ 18th floor main staircase side ✔ 22nd floor plastered work in progress ✔ External plaster in progress “TOWER TRANCE” ✔
Client

Construction Update as on 09-February-2018

By ClientClient/ no comments
  ✔ Tower “JAZZ” 19th floor plaster work in progress. ✔ Tower “JAZZ” Toilet wall tiles 9th floor in progress. ✔ Tower “JAZZ” External plaster in progress. ✔ Tower ”
Client

Construction Update as on 22-December-2017

By ClientClient/ no comments
✔ “Tower B-JAZZ” Finishing work going on. ✔ “Tower A-POP” 7th floor casting & brick work started. ✔ “Tower C-TRANCE: 22nd floor running and 18th floor brick work started. ✔
Client

Construction Update as on 26-October-2017

By ClientClient/ no comments
✔ Tower “JAZZ” 22nd floor structure completed – brick work completed till 20th. ✔ Tower “TRANCE” 20th floor structure completed – brick work completed till 16th. ✔ Tower “POP” 6th floor structure completed.
Client

Construction Update as on 07-October-2017

By ClientClient/ no comments